Rutter Ave Bridge Project

Tomorrow September 19, 2017 milling the approach roadways of Phase 2 is scheduled on the Rutter Avenue Bridge.  

Friday September 22, 2017 paving the approach roadways of Phase 2 is scheduled.

Work during the week of September 25, 2017 will conclude with a traffic shift back to the original configuration by September 29, 2017.

Work schedule is weather dependent.

Expect minor delays during the next two weeks while the milling, paving, and permanent pavement marking operations take place.

Motorists should slow down while travelling through any work zone.